Continuity Report
Knowledge transfer - Sr. Maintenance Mechanic
Executive summary
Ray Delgado holds concentrated, largely tacit responsibility for Plant 2’s Line 3 palletizer and boiler room - systems where he has, until now, been the only person who could recover a failure. Across four capture sessions, in-scope coverage rose from 0 to 79/100, and the number of tasks with a single point of failure fell from 7 to 2. No critical gaps remain open. Two areas still depend on Ray’s hands-on judgment, and both carry a dated plan below that closes them before his departure.
01 · Critical systems & current understanding
- Line 3 palletizer - was Ray only; now documented with Marcus shadowing. Status: watch.
- Boiler start & shutdown - documented; one supervised run pending.
- Die-cutter setup - partially captured; judgment-heavy.
- PM route & utilities - written and transferable.
02 · Tacit knowledge captured
- Chatter diagnosis: cold-vs-warm chatter plus pre-load amp draw tells a worn bearing from a drive fault - a $60 fix mistaken for a $2,000 one.
- OEM deviation: palletizer acceleration set ~15% below default to stop nuisance trips; "restore defaults" brings the fault back.
- Safety step: the pneumatic accumulator must be bled before lockout - a step the written LOTO omits.
- Supply chain: a direct vendor line that ships same-day and a bearing cross-reference, neither in the CMMS.
03 · Risks & mitigations
- High - palletizer recovery still hands-on. Marcus shadows two live recoveries. Owner: Ray, wk 3-6.
- High - LOTO omits stored pneumatic energy. Reissue with the accumulator bleed. Owner: Safety, wk 2.
- Med - annual shutdown never led by successor. One supervised run. Owner: Ray + Marcus, wk 8.
- Med - OEM-deviation values only in memory. Record in CMMS. Owner: Ray, wk 2.
04 · Successor readiness - Marcus Bell
Marcus already runs the PM route and routine corrective work unaided. He is close on palletizer recovery - two shadowed sessions should close it - and not yet independent on the annual shutdown, which is calendar-bound. Recommendation: certify palletizer recovery after the second shadowed run; schedule the supervised shutdown in week 8; hold formal readiness sign-off for the plant manager, who cannot self-certify.